Public Procurement Rules 2004
150 questions · Judiciary
-
Question 1 of 150
Under Rule 2, a procedure whereby all interested persons, firms, or organizations may bid for a contract is termed:
-
Question 2 of 150
Under Rule 16(3), only suppliers or contractors who have been pre-qualified are entitled to:
-
Question 3 of 150
Under Rule 36(d), the two stage - two envelope bidding procedure involves, at the second stage, bidders submitting a revised technical proposal along with a:
-
Question 4 of 150
Under Rule 13(1), the minimum response time for international competitive bidding, from the date of publication, is:
-
Question 5 of 150
Under Rule 19(4), a bidder blacklisted by a foreign country or international organization shall be treated in Pakistan as:
-
Question 6 of 150
Under Rule 2, a person who submits a bid is called a:
-
Question 7 of 150
Under Rule 16A, framework agreements for recurrent or common use items may be arranged for a maximum period of:
-
Question 8 of 150
Under Rule 7A, procuring agencies may carry out e-procurement covering any or all aspects of the procurement process, in accordance with:
-
Question 9 of 150
Under Rule 37(b), two-stage bidding is appropriate for large and complex contracts where:
-
Question 10 of 150
Under Schedule-I, for LNG/LPG procurement, the minimum bid validity period after issuance of the evaluation report is:
-
Question 11 of 150
Under Rule 27, if a procuring agency needs to extend the deadline for submission of bids, it must record reasons in writing and:
-
Question 12 of 150
Under Rule 40(1), negotiations with a successful bidder, without changing cost or scope, may cover methodology, work plan, staffing, and:
-
Question 13 of 150
Under Rule 19(1)(b), before initiating blacklisting for breach of contract, the procuring agency must first:
-
Question 14 of 150
Under Rule 38B, a single responsive bid in goods, works, and services may be considered by the procuring agency if it meets the evaluation criteria, is not in conflict with the Ordinance, conforms to specifications, and:
-
Question 15 of 150
Under Rule 16A(4), the maximum duration of an open framework agreement is three years, while a closed framework agreement's maximum duration is:
-
Question 16 of 150
Under Rule 2, the assignment of a procuring agency's procurement functions to another public sector entity to perform those functions on its behalf is termed:
-
Question 17 of 150
Under Rule 42(c)(iii), direct contracting for compatibility reasons (to avoid technical incompatibility with existing equipment) is subject to a maximum contract duration of:
-
Question 18 of 150
Under Rule 6, communications and documentation related to Federal Government procurements shall be in:
-
Question 19 of 150
Under Rule 37(c), the two stage - two envelope method is appropriate where alternative technical proposals are possible, such as for:
-
Question 20 of 150
Under Rule 2, a proposal containing a unique and innovative idea, not submitted in response to any procurement request but aligned with the procuring agency's objectives, is termed a(n):
-
Question 21 of 150
Under Rule 43, procuring agencies must make prompt payments to suppliers and contractors against invoices or running bills within a time not exceeding:
-
Question 22 of 150
Under Rule 45(2), a defect liability certificate shall be issued within thirty days of the expiry of the defect liability period, and (except for unsettled claims resolved through arbitration) the final bill shall be paid within a time not exceeding:
-
Question 23 of 150
Under Rule 10(3), where a reference to a brand name or catalogue number is unavoidable to complete a specification, the procuring agency must add which words?
-
Question 24 of 150
Under Rule 38, the bidder with the most advantageous bid shall be awarded the contract, provided it is not in conflict with any other law, rules, regulations, or policy, and the award occurs within:
-
Question 25 of 150
Under Rule 2, a bidder declared untrustworthy by the Authority due to corrupt or fraudulent practice, established performance failure, or deviation from a prior commitment is termed:
-
Question 26 of 150
Under Rule 47, once a contract is awarded, the procuring agency shall make documents related to evaluation and award public, except where disclosure is proprietary or against public interest, subject to:
-
Question 27 of 150
Under Rule 21, procuring agencies must use open competitive bidding if the cost of the object to be procured is more than:
-
Question 28 of 150
Under Rule 37, the single stage - one envelope bidding procedure is ordinarily used as:
-
Question 29 of 150
Under Rule 28(2), all bids submitted after the prescribed time shall be:
-
Question 30 of 150
Under Rule 18, a procuring agency shall disqualify a supplier or contractor if it finds that information submitted concerning qualification was:
-
Question 31 of 150
Under the proviso to Rule 36(c), if the procuring agency revises technical requirements during two-stage bidding, sufficient time must be allowed to bidders, not less than:
-
Question 32 of 150
Under Rule 2, harming or threatening to harm persons to influence their participation in a procurement process is termed:
-
Question 33 of 150
Under Rule 42(b), the request for quotations method applies where procurement value is more than Rs. 100,000 but does not exceed:
-
Question 34 of 150
The body established under the Public Procurement Regulatory Authority Ordinance, 2002 to regulate public procurement in Pakistan is commonly known by which acronym?
-
Question 35 of 150
Under Rule 48(6), the Grievance Redressal Committee (GRC) must investigate and decide upon a complaint within:
-
Question 36 of 150
Under Rule 2, the use of information and communication technologies or digital/electronic means for the procurement process is defined as:
-
Question 37 of 150
Under Rule 34, if a procuring agency rejects all bids, before calling for re-bidding it should:
-
Question 38 of 150
Under Rule 2, a person, consultant, firm, company, or organization that undertakes to supply goods, services, or works is defined (in two separate but overlapping definitions) as a:
ExplanationThe Rules separately define both 'contractor' and 'supplier' using essentially the same wording -- a person or entity undertaking to supply goods, services, or works.
-
Question 39 of 150
Under Rule 2, 'coercive practices' in procurement refer to:
-
Question 40 of 150
Under Rule 17, a procuring agency may require additional information about a supplier's competence at any stage, provided such requirement is:
-
Question 41 of 150
Under Rule 19(1)(b), if a bidder fails to perform contractual obligations or breaches the contract, blacklisting may be imposed for a period of not more than:
-
Question 42 of 150
Under Rule 36(c)(v), bidders unwilling to conform their technical proposals to the procuring agency's requirements in two-stage bidding may withdraw:
-
Question 43 of 150
Considering Rules 19(1)(a), (b), and (c) together, which of the following correctly ranks the maximum blacklisting periods from LONGEST to SHORTEST?
ExplanationThis reflects the graduated severity built into Rule 19: corrupt/fraudulent practice carries the harshest penalty (up to 10 years), followed by contractual breach (up to 3 years), and then failure to honour a bid securing declaration (up to 6 months).
-
Question 44 of 150
Under Rule 20, the principal method of procurement to be used by procuring agencies is:
-
Question 45 of 150
Under Rule 37A(1), an unsolicited proposal received by a procuring agency is first assessed by an assessment committee comprising at least:
-
Question 46 of 150
Under Rule 51, the Public Procurement Rules, 2004 have effect notwithstanding anything to the contrary in:
-
Question 47 of 150
Under Rule 15(2), factors a procuring agency may consider during pre-qualification include relevant experience, financial position, appropriate managerial capability, and:
-
Question 48 of 150
The Public Procurement Regulatory Authority Ordinance, under which the 2004 Rules were made, is numbered as:
-
Question 49 of 150
Under Rule 36(a), in the single stage - one envelope procedure, each bid comprises:
-
Question 50 of 150
Under Rule 42(e), one of the conditions justifying use of force account is that the required works are:
-
Question 51 of 150
Under Rule 50, any unauthorized breach of the Public Procurement Rules, 2004 amounts to:
-
Question 52 of 150
Under Rule 1(2), the Public Procurement Rules, 2004 came into force:
-
Question 53 of 150
Under Rule 37A(1)(d), if a viable unsolicited proposal proceeds to competitive bidding, the original proponent is awarded what additional weightage in the combined evaluation?
-
Question 54 of 150
Under Rule 32, in assessing whether a bidding condition is discriminatory or difficult to meet, reference shall be made to:
-
Question 55 of 150
Under Rule 48(3), a bidder aggrieved after submission of a bid may lodge a written complaint within seven days of the technical evaluation report, or within how many days after the final evaluation report?
-
Question 56 of 150
Under Rule 41, information regarding technical or final evaluation shall be kept confidential until:
-
Question 57 of 150
Under Rule 42(d), negotiated tendering may be used where supplies are manufactured purely to support a specific research project, experiment, study, or development, or where, for technical/artistic reasons, supplies can only be delivered by:
-
Question 58 of 150
Under Rule 4, the core principles procuring agencies must ensure during procurement include a fair and transparent process, value for money, and:
-
Question 59 of 150
Under Rule 8, procuring agencies were required to devise a procurement planning mechanism within:
-
Question 60 of 150
Under Rule 11, procuring agencies must provide clear authorization and delegation of powers, and shall only initiate procurements once:
-
Question 61 of 150
Under Rule 21-A(3), advertisements for import of Schedule-I commodities must be published in at least how many widely circulated daily newspapers or journals?
-
Question 62 of 150
Under Rule 42(d)(iii), negotiated tendering may also be used in cases of extreme urgency, provided the urgency:
-
Question 63 of 150
Under Rule 36(b)(viii), financial proposals of bidders found technically non-responsive shall be:
-
Question 64 of 150
Under Rule 29, failure to provide an unambiguous evaluation criteria in the bidding documents amounts to:
-
Question 65 of 150
Under what authority were the Public Procurement Rules, 2004 made?
-
Question 66 of 150
Under Rule 19(5), a blacklisted or debarred bidder already engaged in an ongoing public contract:
-
Question 67 of 150
Under Rule 36(c), the two-stage bidding procedure begins with bidders submitting:
-
Question 68 of 150
Under Rule 26(4)(c), a bidder who does NOT agree to an extension of bid validity shall be allowed to:
-
Question 69 of 150
Under Rule 19(3), the Authority must decide a review petition against blacklisting within:
-
Question 70 of 150
Under Rule 2, procurement of the same commodity from the same source without competition, including enhancement of contracts, is defined as:
-
Question 71 of 150
Under Rule 2, an agreement with specified terms and conditions AND an agreed price is termed a:
ExplanationA closed framework agreement fixes both the terms/conditions and the price in advance, unlike an open framework agreement, which fixes terms but not price.
-
Question 72 of 150
Under Rule 19(3), a bidder aggrieved by a blacklisting decision may file a review petition before the Authority within:
-
Question 73 of 150
Under Rule 2, an arrangement between two or more parties designed to stifle open competition and fix prices at artificial, non-competitive levels is termed:
-
Question 74 of 150
Under the historical amendment referenced in Rule 13, what word was originally used before being replaced with 'days' for the response time periods?
ExplanationThe phrase 'working days' was substituted with 'days' by S.R.O. 1241(I)/2006.
-
Question 75 of 150
Under Rule 39, a performance guarantee required from a successful bidder shall not exceed what percentage of the contract amount?
-
Question 76 of 150
Under Rule 48(1), a procuring agency must constitute a grievance redressal committee comprising:
-
Question 77 of 150
Under Rule 42(f)(iii), where more than one state-owned entity is eligible under direct contracting, the procuring agency shall:
-
Question 78 of 150
Under Rule 45(1), the overall delivery certificate or taking-over certificate, marking the close of contract performance, shall be issued within:
-
Question 79 of 150
Under the proviso to Rule 25, where a procuring agency does not require bid security, the bidder shall instead submit a:
-
Question 80 of 150
Under Rule 44(b), where a written contract is required, the contract comes into force from the date on which:
-
Question 81 of 150
Under Rule 2, an order placed by a procuring agency under general terms and pricing on a range of goods under a closed framework agreement, without negotiating terms each time, is called a:
-
Question 82 of 150
Under Rule 19(1)(c), if a bidder fails to abide by a bid securing declaration (without corrupt/fraudulent practice), blacklisting may be imposed for a period of not more than:
-
Question 83 of 150
Under Rule 42(c)(i), direct contracting is permissible for acquisition of spare parts or supplementary services from the original manufacturer, provided:
-
Question 84 of 150
Under the proviso to Rule 51, prior rules and procedures remain applicable only for procurements where:
-
Question 85 of 150
Under Rule 10(1), specifications must be defined so as to:
-
Question 86 of 150
Under Rule 42(c)(iv), direct contracting through repeat orders is permissible up to what percentage of the original procurement?
-
Question 87 of 150
Under Rule 35, the final evaluation report must be announced, giving justification for acceptance or rejection, at least how many days prior to the award of the procurement contract?
-
Question 88 of 150
Under Rule 42(b)(iv), in the request for quotations method, the object of procurement is purchased from the supplier offering:
-
Question 89 of 150
Under Rule 2, a 'bid' is defined as:
-
Question 90 of 150
Under Rule 28(1), bids shall be opened at a time specified in the bidding documents, and at least:
-
Question 91 of 150
Under Rule 23(2), bidding documents for competitive bidding must include the invitation to bid, instructions to bidders, form of bid and contract, and, among others:
-
Question 92 of 150
Under Rule 25, a procuring agency may require bid security not exceeding what percentage of the estimated procurement value?
-
Question 93 of 150
Under Rule 13(3), where advertisement occurs in both print and electronic media, the response time is calculated from:
-
Question 94 of 150
Under Rule 37(a), the single stage - two envelope procedure is used where bids are to be evaluated on:
-
Question 95 of 150
Under Rule 42(a), the contract document typically used for petty purchases is a:
-
Question 96 of 150
Under Rule 13(1), the minimum response time for national competitive bidding, from the date of publication, is:
-
Question 97 of 150
Under Rule 14, mandatory advertisement of procurement requirements may be deviated from, with prior Authority approval, where the procurement relates to:
-
Question 98 of 150
Under Rule 46(1), procuring agencies must maintain a record of procurement proceedings and associated documentation for a minimum period of:
-
Question 99 of 150
Under Rule 3, the Public Procurement Rules, 2004 apply to procurements made by:
-
Question 100 of 150
The Public Procurement Rules, 2004 were notified vide which S.R.O.?
ExplanationS.R.O. 432(I)/2004 is the original notification of the Public Procurement Rules, 2004, dated 9 June 2004; the other S.R.O.s cited relate to subsequent amendments.
-
Question 101 of 150
Under Rule 10(4), solicitation documents for disposal of assets by tender shall specify that the asset is sold on which basis?
-
Question 102 of 150
Under Rule 2, natural calamities, disasters, accidents, war, or operational situations requiring prompt action are collectively termed:
-
Question 103 of 150
Under Rule 21-A, for import of commodities to meet a demand-supply gap (as listed in Schedule-I), which bidding procedure must be adopted?
-
Question 104 of 150
Under Rule 42(a), petty purchases through single quotation, without bidding, apply where the value of procurement is up to:
-
Question 105 of 150
Under Rule 44(a), where no formal signing of a contract is required, the contract comes into force from the date:
-
Question 106 of 150
Under the proviso to Rule 28(2), live broadcast of the bid opening on the procuring agency's website or digital channel is required if the volume of procurement for works exceeds Rs. 1 billion, or for goods and services exceeds:
-
Question 107 of 150
Under Rule 22(1), bids shall be submitted:
-
Question 108 of 150
Under Rule 45A, a procuring agency may assign whole or part of its procurement process to another procuring agency, provided:
-
Question 109 of 150
Comparing Rule 12(1) and Rule 12(2), procurement advertisement requirements escalate from website-only (or website plus optional print) to mandatory print-plus-website publication once the value crosses which threshold?
-
Question 110 of 150
Under Rule 12(1), procurements over Rs. 500,000 and up to Rs. 3,000,000 shall be advertised on:
ExplanationThe upper threshold for website-only advertisement was raised from Rs. 2 million to Rs. 3 million by S.R.O. 442(I)/2020.
-
Question 111 of 150
Under Rule 49(1), after a procurement contract comes into force, disputes between the parties shall be settled by:
-
Question 112 of 150
Under Rule 12(2), procurement opportunities exceeding Rs. 3,000,000 must be advertised on the Authority's website as well as in newspapers, specifically in at least:
-
Question 113 of 150
Under Rule 6(3), in case of a dispute over language, reference shall be made to:
-
Question 114 of 150
Under Rule 42(b)(i), quotations for this method must be requested from:
-
Question 115 of 150
Under Rule 37A(3), if the initiator of an unsolicited proposal does not emerge as the most advantageous bid, the initiator is given an opportunity to:
-
Question 116 of 150
Under Rule 26(3), if bid validity needs to be extended beyond the originally specified period, the extension shall not exceed:
-
Question 117 of 150
Under Rule 42(c)(vii), direct contracting is permitted for the purchase of motor vehicles from local original manufacturers or their authorized agents, at:
-
Question 118 of 150
Under Rule 2, if a bidder is debarred by one procuring agency, that bidder is treated by all other procuring agencies as:
-
Question 119 of 150
Under Rule 2, a bid found substantially responsive after meeting eligibility criteria and evaluated as the highest ranked on cost, quality, or a combination thereof is termed the:
ExplanationThe term 'lowest evaluated bid' was replaced throughout the Rules with 'most advantageous bid' by amendment (S.R.O. 442(I)/2020), reflecting a shift from price-only evaluation.
-
Question 120 of 150
Under Rule 5, where these Rules conflict with an international treaty or agreement of the Federal Government, which prevails?
-
Question 121 of 150
Under Rule 30(2), for comparing bids quoted in different currencies, conversion shall use the selling rate notified by which institution on the date of bid opening?
-
Question 122 of 150
Under Rule 2, 'value for money' is defined with reference to best returns for each rupee spent, considering quality, timeliness, reliability, and:
-
Question 123 of 150
Under Rule 33(1), a procuring agency may reject all bids at any time prior to acceptance, and upon request must communicate to bidders the grounds for rejection, but is:
-
Question 124 of 150
Under Rule 15(1), pre-qualification of bidders may be used particularly for services, civil works, turnkey projects, and:
-
Question 125 of 150
Under Rule 36(b), in the single stage - two envelope procedure, the envelope marked 'FINANCIAL PROPOSAL' is:
-
Question 126 of 150
Under Rule 7, procurements exceeding a prescribed limit are subject to an:
-
Question 127 of 150
Under Rule 48(7), a bidder dissatisfied with the GRC's decision may file an appeal before the Authority within:
-
Question 128 of 150
Under Rule 48(4), if a complaint is filed against the technical evaluation report, the GRC's immediate action is to:
-
Question 129 of 150
Which of the following best describes the overall purpose of the Public Procurement Rules, 2004, as reflected throughout the Rules?
-
Question 130 of 150
Under Rule 42(f), direct contracting with state-owned entities for time-sensitive, public-interest works and services requires the engaged organization to accomplish the work:
-
Question 131 of 150
Under Rule 2, execution of small works or non-consultancy services through direct contracting with a state-owned entity having the necessary resources, subject to cost and time effectiveness, is termed:
-
Question 132 of 150
Considering Rules 25 and 39 together, which statement correctly compares bid security and performance guarantee ceilings?
-
Question 133 of 150
Under Rule 2, an agreement with specified terms and conditions but WITHOUT an agreed price is termed a(n):
-
Question 134 of 150
Under Rule 2, the offering, giving, receiving, or soliciting of anything of value to influence the acts of another party for wrongful gain is termed:
-
Question 135 of 150
Under Rule 42(e), force account may be used if the value of procurement does not exceed:
-
Question 136 of 150
Under Rule 24(1), procuring agencies shall generally allow prospective bidders to participate in procurement proceedings:
-
Question 137 of 150
Which of the following procurement methods under Rule 42 is generally considered an EXCEPTION to open competitive bidding rather than the default method?
-
Question 138 of 150
Under the proviso to Rule 13(1), no minimum response time is applicable in case of:
-
Question 139 of 150
Under Rule 39A, a letter of credit provision may be incorporated where shipments and customs clearance are involved, referencing standard terms issued by:
-
Question 140 of 150
Under Schedule-I, for agricultural products such as fertilizer, grains, and sugar, the minimum response time from advertisement is:
-
Question 141 of 150
Under the proviso to Rule 38B(1), in what type of proceedings shall a single bid NOT be entertained (except in the case of an unsolicited proposal)?
-
Question 142 of 150
Under Rule 19(1)(a), if corrupt and fraudulent practice is established against a bidder, blacklisting and cross-debarment may be imposed for a period of not more than:
-
Question 143 of 150
Under Schedule-I, for petroleum products (such as motor gasoline, HSD, and jet fuel), the minimum response time from advertisement is:
-
Question 144 of 150
Under Rule 9, a procuring agency shall announce all proposed procurements for a financial year and proceed without:
-
Question 145 of 150
Under Schedule-I, for LNG/LPG, the minimum response time from advertisement is:
-
Question 146 of 150
Under Rule 2, an act or omission, including misrepresentation, that knowingly or recklessly misleads a party to obtain a benefit or avoid an obligation is termed:
-
Question 147 of 150
Under Rule 23(3), information that becomes necessary for bidding after the invitation to bid must be provided:
-
Question 148 of 150
Under Rule 31(1), after bids are opened, a bidder is not allowed to alter or modify the bid, but the procuring agency may:
-
Question 149 of 150
Under Schedule-I, the minimum bid validity period after issuance of the evaluation report for agricultural products and petroleum products alike is:
-
Question 150 of 150
Under the first proviso to Rule 42(e), a state-owned entity engaged for force-account work must accomplish the task: